🙏 Thanks to the BDA team — Niranjan (EE), Inbavalli (AEE), Sushma (EE) and Vinayak — and the Hombale team, led by Gunashekar (DGM), for their prompt response and support in making this progress possible.
Resident progress tracker

Skandagiri Phase 2 Works Dashboard

A consolidated, resident-friendly view of completed, in-progress and pending infrastructure works for Skandagiri Apartment, Konadasapura.

Society: Skandagiri ApartmentPhase 2, KonadasapuraUpdated: July 2026Prepared by Managing Committee
Skandagiri Resident Welfare Association seal

Overall completion

25%16 of 65 tracked items completed
Completed16Major items closed
In Progress19Currently being worked on
Pending30Awaiting action or closure
Total Tracked65Across 4 work categories

Current Progress Snapshot

Completed 16 / In Progress 19 / Pending 30

CompletedIn ProgressPending
🏆 Major winsD & E Block ATS rectified, MCB issues in A, D & E Blocks rectified, quarterly lift maintenance done, STP controller & generator automation, CCTV, lift AMC, streetlight repairs, parking data consolidation and debris removal are completed.
Current focusBoundary wall work, motor installation (14 received), speed breakers, locking shaft/missing doors, Cauvery water connection (with BWSSB), KSPCB consent renewal, park work (jogging track, play area & gazebo), and Y-strainer installation.
Next priorityRestoring failed borewells, water filtration, RWH, basement seepage, silt filtration, STP tank health hazard, waste segregation, DG/transformer/earth-pit maintenance, boom barrier and park development.

Status by Type

Grouped by work category for easier tracking and follow-up.

1. Water Supply & Plumbing

4 Done5 In Progress10 Pending
💧
Done
  • Existing borewells: 1 of 4 working — motor repair completed. CATEGORY 1
  • New borewells: 2 of 5 drilled borewells have motors fitted and are operational. CATEGORY 1
  • STP controller integrated and Generator made automatic. CATEGORY 1
  • STP tank cleaning completed — sludge cleared, system cleaned, motor servicing coordinated. CATEGORY 1
In Progress
  • Motors: 14 new motors received in 2 batches — 4 installed & commissioned, 2 defective (warranty replacement pending), remaining installation in phases.
  • Fresh water automation controller — installation in progress.
  • New borewells: 2 of 5 drilled borewells still need motors fitted. CATEGORY 1
  • Y-strainer installation — in progress (Niranjan EE).
  • Cauvery Water Connection — formal request submitted, BDA coordinating with BWSSB, site inspection expected within days. CATEGORY 1
Not Done / Pending
  • Existing borewells: 3 of 4 have failed — near A block, near B block, and in Labour Colony — will not be restored. CATEGORY 1
  • New borewells: 1 of 5 drilled failed — no water found. CATEGORY 1
  • Yield reports pending for all new borewells — follow-up with Vinayak (Hombale). CATEGORY 1
  • Plumbing & blockages — 70+ flats being checked. CATEGORY 1
  • Water filtration system. CATEGORY 1
  • Exit valve pending for all fresh water connections. CATEGORY 1
  • Rainwater Harvesting — tanks to be cleaned, motor/pump to be installed. CATEGORY 1
  • Basement seepage — expansion joints (opened during basement cleaning) to be sealed.
  • Silt accumulation in pipes — ground sump-level filtration solution needed. CATEGORY 1
  • STP overhead tank discolored water (health hazard) — sediment reaching flats since motors aren't installed with auto-controller yet. Responsible: Niranjan EE, Inbavalli AEE, Gunashekhar (Hombale). CATEGORY 1

2. Civil & General Maintenance

4 Done3 In Progress7 Pending
🏗️
Done
  • Maintenance of floors and basement.
  • Construction debris removed from common areas.
  • Exit ramp blockage issue resolved.
  • Parking data consolidated and updated through MyGate for easier tracking.
In Progress
  • Boundary wall construction on STP side started last week.
  • Locking shaft doors & missing doors — list being compiled from members; Gunashekhar (Hombale) to rectify.
  • ⚠ Back wall stagnated due to issue with the plan — security concern; Inbavalli AEE & Niranjan EE to discuss with RCCL & Hombale to resolve ASAP.
Not Done / Pending
  • Entry & exit slab replacement — stalled; following up with Gunashekhar Sir (Hombale) for months, no visible update yet.
  • Basement parking water flooding solution.
  • Flooding near electric room / open ducts.
  • Second coat of painting.
  • Front gate elevation as per approved plan.
  • De-weeding of car parking areas.
  • Basement seepage — expansion joints to be sealed.

3. Electrical, Fire & Safety

7 Done7 In Progress6 Pending
Done
  • Lift AMC completed.
  • Common area streetlight repairs completed.
  • E Block ATS (Automatic Transfer Switch) — rectified.
  • D Block ATS — rectified.
  • Quarterly lift maintenance (6 July 2026) — done.
  • MCB electrical issues in A, D and E Blocks — rectified.
  • Follow-up with Ranjith Electrical Contractor (BDA) on MCB-related work — completed.
In Progress
  • ⚠ CCTV Recording NOT Working: 5 cameras currently installed, but recording system (NVR/HDD) is non-functional; follow-up with Inbavalli AEE & Gunashekhar (Hombale). CATEGORY 1
  • Speed breakers — discussion in progress on locations and specs; contractor to visit site for installation.
  • KSPCB Consent Renewal — show-cause notice, renewal in progress (Inbavalli AEE).
  • Boom barrier — requested for vehicle entry tracking.
  • Parking allotment/numbering (Konadasapura Phase 2) — flagged for discussion with BDA.
  • ⚠ Fire extinguisher refill — expiring end of this month, urgent renewal required. Inbavalli AEE to follow up. CATEGORY 1
  • Earth Pits Maintenance: 15 of 26 pits recovered, 11 more to go. JCB required — requested from Inbavalli AEE & Gunashekhar (Hombale).
Not Done / Pending
  • Common area tube light repairs.
  • DG Set: one missing as per approved plan; DG maintenance & backup DG required (critical during power failure).
  • Exit Gate as per approved plan.
  • Fire alarm systems and fire safety equipment. CATEGORY 1
  • Street lights not working — 3 in front of B & C blocks, towards F block & road, near transformer, parking, and back wall.
  • Transformer maintenance — recent power fluctuations reported in some flats.

4. Park & Environment

5 In Progress7 Pending
🌳
In Progress
  • Park work commenced 16 July — pavement laying underway.
  • Landscaping & debris removal — ongoing.
  • Jogging track construction — commenced.
  • Children's play area & walking track with gazebo — in progress, to be fenced.
  • Remaining park works to follow.
Not Done / Pending
  • Park development.
  • Jogging track.
  • Benches.
  • Lighting improvements.
  • Tree plantation / landscaping.
  • Waste segregation & organic composting — Inbavalli AEE to provide per-block wet/dry bins; Inbavalli AEE to issue work order to Hombale for dedicated STP person and organic waste converter machine, as proposed by Commissioner Sir.
  • Solid Waste Converter — Category 1, person to be assigned.
Note: This dashboard is for resident communication and tracking. Status can be updated after confirmation from BDA, Hombale, or the responsible execution team.