🙏 Thanks to the BDA team — Niranjan (EE), Inbavalli (AEE), Sushma (EE) and Vinayak — and the Hombale team, led by Gunashekar (DGM), for their prompt response and support in making this progress possible.
Resident progress tracker
Skandagiri Phase 2 Works Dashboard
A consolidated, resident-friendly view of completed, in-progress and pending infrastructure works for Skandagiri Apartment, Konadasapura.
Society: Skandagiri ApartmentPhase 2, KonadasapuraUpdated: July 2026Prepared by Managing Committee
Overall completion
25%16 of 65 tracked items completed
Completed16Major items closed
In Progress19Currently being worked on
Pending30Awaiting action or closure
Total Tracked65Across 4 work categories
Current Progress Snapshot
Completed 16 / In Progress 19 / Pending 30
CompletedIn ProgressPending
🏆 Major winsD & E Block ATS rectified, MCB issues in A, D & E Blocks rectified, quarterly lift maintenance done, STP controller & generator automation, CCTV, lift AMC, streetlight repairs, parking data consolidation and debris removal are completed.
Current focusBoundary wall work, motor installation (14 received), speed breakers, locking shaft/missing doors, Cauvery water connection (with BWSSB), KSPCB consent renewal, park work (jogging track, play area & gazebo), and Y-strainer installation.
Next priorityRestoring failed borewells, water filtration, RWH, basement seepage, silt filtration, STP tank health hazard, waste segregation, DG/transformer/earth-pit maintenance, boom barrier and park development.
Status by Type
Grouped by work category for easier tracking and follow-up.
1. Water Supply & Plumbing
4 Done5 In Progress10 Pending
💧
Done
Existing borewells: 1 of 4 working — motor repair completed. CATEGORY 1
New borewells: 2 of 5 drilled borewells have motors fitted and are operational. CATEGORY 1
STP controller integrated and Generator made automatic. CATEGORY 1
STP tank cleaning completed — sludge cleared, system cleaned, motor servicing coordinated. CATEGORY 1
In Progress
Motors: 14 new motors received in 2 batches — 4 installed & commissioned, 2 defective (warranty replacement pending), remaining installation in phases.
Fresh water automation controller — installation in progress.
New borewells: 2 of 5 drilled borewells still need motors fitted. CATEGORY 1
Y-strainer installation — in progress (Niranjan EE).
Cauvery Water Connection — formal request submitted, BDA coordinating with BWSSB, site inspection expected within days. CATEGORY 1
Not Done / Pending
Existing borewells: 3 of 4 have failed — near A block, near B block, and in Labour Colony — will not be restored. CATEGORY 1
New borewells: 1 of 5 drilled failed — no water found. CATEGORY 1
Yield reports pending for all new borewells — follow-up with Vinayak (Hombale). CATEGORY 1
Plumbing & blockages — 70+ flats being checked. CATEGORY 1
Water filtration system. CATEGORY 1
Exit valve pending for all fresh water connections. CATEGORY 1
Rainwater Harvesting — tanks to be cleaned, motor/pump to be installed. CATEGORY 1
Basement seepage — expansion joints (opened during basement cleaning) to be sealed.
STP overhead tank discolored water (health hazard) — sediment reaching flats since motors aren't installed with auto-controller yet. Responsible: Niranjan EE, Inbavalli AEE, Gunashekhar (Hombale). CATEGORY 1
2. Civil & General Maintenance
4 Done3 In Progress7 Pending
🏗️
Done
Maintenance of floors and basement.
Construction debris removed from common areas.
Exit ramp blockage issue resolved.
Parking data consolidated and updated through MyGate for easier tracking.
In Progress
Boundary wall construction on STP side started last week.
Locking shaft doors & missing doors — list being compiled from members; Gunashekhar (Hombale) to rectify.
⚠ Back wall stagnated due to issue with the plan — security concern; Inbavalli AEE & Niranjan EE to discuss with RCCL & Hombale to resolve ASAP.
Not Done / Pending
Entry & exit slab replacement — stalled; following up with Gunashekhar Sir (Hombale) for months, no visible update yet.
Basement parking water flooding solution.
Flooding near electric room / open ducts.
Second coat of painting.
Front gate elevation as per approved plan.
De-weeding of car parking areas.
Basement seepage — expansion joints to be sealed.
3. Electrical, Fire & Safety
7 Done7 In Progress6 Pending
⚡
Done
Lift AMC completed.
Common area streetlight repairs completed.
E Block ATS (Automatic Transfer Switch) — rectified.
D Block ATS — rectified.
Quarterly lift maintenance (6 July 2026) — done.
MCB electrical issues in A, D and E Blocks — rectified.
Follow-up with Ranjith Electrical Contractor (BDA) on MCB-related work — completed.
In Progress
⚠ CCTV Recording NOT Working: 5 cameras currently installed, but recording system (NVR/HDD) is non-functional; follow-up with Inbavalli AEE & Gunashekhar (Hombale). CATEGORY 1
Speed breakers — discussion in progress on locations and specs; contractor to visit site for installation.
Boom barrier — requested for vehicle entry tracking.
Parking allotment/numbering (Konadasapura Phase 2) — flagged for discussion with BDA.
⚠ Fire extinguisher refill — expiring end of this month, urgent renewal required. Inbavalli AEE to follow up. CATEGORY 1
Earth Pits Maintenance: 15 of 26 pits recovered, 11 more to go. JCB required — requested from Inbavalli AEE & Gunashekhar (Hombale).
Not Done / Pending
Common area tube light repairs.
DG Set: one missing as per approved plan; DG maintenance & backup DG required (critical during power failure).
Exit Gate as per approved plan.
Fire alarm systems and fire safety equipment. CATEGORY 1
Street lights not working — 3 in front of B & C blocks, towards F block & road, near transformer, parking, and back wall.
Transformer maintenance — recent power fluctuations reported in some flats.
4. Park & Environment
5 In Progress7 Pending
🌳
In Progress
Park work commenced 16 July — pavement laying underway.
Landscaping & debris removal — ongoing.
Jogging track construction — commenced.
Children's play area & walking track with gazebo — in progress, to be fenced.
Remaining park works to follow.
Not Done / Pending
Park development.
Jogging track.
Benches.
Lighting improvements.
Tree plantation / landscaping.
Waste segregation & organic composting — Inbavalli AEE to provide per-block wet/dry bins; Inbavalli AEE to issue work order to Hombale for dedicated STP person and organic waste converter machine, as proposed by Commissioner Sir.
Solid Waste Converter — Category 1, person to be assigned.
Note: This dashboard is for resident communication and tracking. Status can be updated after confirmation from BDA, Hombale, or the responsible execution team.
Skandagiri Residents Welfare Association • Progress Dashboard