🙏 Thanks to the BDA team — Niranjan (EE), Inbavalli (AEE), Sushma (EE) and Vinayak — and the Hombale team, led by Gunashekar (DGM), for their prompt response and support in making this progress possible.
Resident progress tracker

Skandagiri Phase 2 Works Dashboard

A consolidated, resident-friendly view of completed, in-progress and pending infrastructure works for Skandagiri Apartment, Konadasapura.

Society: Skandagiri ApartmentPhase 2, KonadasapuraUpdated: July 2026Prepared by Managing Committee
Skandagiri Resident Welfare Association seal

Overall completion

28%10 of 36 tracked items completed
Completed10Major items closed
In Progress4Currently being worked on
Pending23Awaiting action or closure
Total Tracked36Across 4 work categories

Current Progress Snapshot

Completed 10 / In Progress 4 / Pending 23

CompletedIn ProgressPending
🏆 Major winsBorewells, 6 serviced motors, automatic water controller, STP cleaning, CCTV, lift AMC, streetlight repairs, parking data consolidation and debris removal are completed.
Current focusBoundary wall work and MCB issues in A, D & E Blocks.
Next priorityWater filtration, flooding fixes, fire safety and park development.

Status by Type

Grouped by work category for easier tracking and follow-up.

1. Water Supply & Plumbing

3 Done6 Pending
💧
Done
  • Borewells: all 4 borewells are operational.
  • Each borewell is yielding approximately 1.5-inch water for around 3 hours.
  • External borewell has been secured with a protective cover.
  • Automatic Water Level Controller completed for both Fresh Water and STP systems.
  • 6 motors have been serviced and are available for water system operations.
  • STP tank cleaning completed.
Not Done / Pending
  • Water filtration system.
  • Broken / blocked drainage gratings.
  • Sludge cleanup in basement.
  • Cleaning of Rain Water Harvesting sump.
  • Rainwater logging in common areas.
  • 7th floor pressure reducing valve repairs.

2. Civil & General Maintenance

4 Done1 In Progress5 Pending
🏗️
Done
  • Maintenance of floors and basement.
  • Construction debris removed from common areas.
  • Exit ramp blockage issue resolved.
  • Parking data consolidated and updated through MyGate for easier tracking.
In Progress
  • Boundary wall construction on STP side started last week.
Not Done / Pending
  • Basement parking water flooding solution.
  • Flooding near electric room / open ducts.
  • Second coat of painting.
  • Front gate elevation as per approved plan.
  • De-weeding of car parking areas.

3. Electrical, Fire & Safety

3 Done2 In Progress6 Pending
Done
  • CCTV installation with monitoring from front gate security cabin.
  • Lift AMC completed.
  • Common area streetlight repairs completed.
In Progress
  • MCB electrical issues in A, D and E Blocks are in progress.
  • Quarterly lift maintenance is scheduled for tomorrow, 6 July 2026.
  • Follow-up is being done with Hombale for remaining MCB-related work.
Not Done / Pending
  • Common area tube light repairs.
  • DG Set: one missing as per approved plan.
  • Exit Gate as per approved plan.
  • Locking of shaft doors on every floor.
  • Speed breakers and barricades.
  • Fire extinguishers, fire alarm systems and fire safety equipment.

4. Park & Environment

1 In Progress6 Pending
🌳
In Progress
  • Park levelling.
Not Done / Pending
  • Park development.
  • Jogging track.
  • Benches.
  • Lighting improvements.
  • Tree plantation / landscaping.
  • Organic Water Converter and demo.
Note: This dashboard is for resident communication and tracking. Status can be updated after confirmation from BDA, Hombale, or the responsible execution team.