🙏 Thanks to the BDA team — Niranjan (EE), Inbavalli (AEE), Sushma (EE) and Vinayak — and the Hombale team, led by Gunashekar (DGM), for their prompt response and support in making this progress possible.
Resident progress tracker

Skandagiri Phase 2 Works Dashboard

A consolidated, resident-friendly view of completed, in-progress and pending infrastructure works for Skandagiri Apartment, Konadasapura.

Society: Skandagiri ApartmentPhase 2, KonadasapuraUpdated: September 2026Prepared by Managing Committee
Skandagiri Resident Welfare Association seal

Overall completion

29%23 of 80 tracked items completed
Completed23Major items closed
In Progress31Currently being worked on
Pending26Awaiting action or closure
Total Tracked80Across 4 work categories

Current Progress Snapshot

Completed 23 / In Progress 31 / Pending 26

CompletedIn ProgressPending
🏆 Major winsD & E Block ATS rectified (BESCOM & AXON), MCB issues in A, D & E Blocks rectified, annual lift maintenance done for 5 of 6 blocks (A Block pending), STP controller & generator automation, CCTV, lift AMC, streetlight repairs, parking data consolidation and debris removal are completed.
Current focusFMS handover before Hombale services end this month (ad-hoc association to be formed), Boundary wall work, motor installation (2 defective replacements), basement speed breaker (stilt done 21 Aug), locking shaft/missing doors, Cauvery water connection (with BWSSB), KSPCB consent renewal, and park work (jogging track, play area & gazebo).
Next priorityRestoring failed borewells, water filtration, RWH, basement seepage, silt filtration, STP tank health hazard, waste segregation, DG/transformer/earth-pit maintenance, boom barrier and park development.

Status by Type

Grouped by work category for easier tracking and follow-up.

1. Water Supply & Plumbing

8 Done5 In Progress8 Pending
💧
Done
  • Existing borewells: 1 of 4 working — motor repair completed. CATEGORY 1
  • New borewells: 2 of 5 drilled borewells have motors fitted and are operational. CATEGORY 1
  • STP controller integrated and Generator made automatic. CATEGORY 1
  • STP tank cleaning completed — sludge cleared, system cleaned, motor servicing coordinated. CATEGORY 1
  • Motors: All 14 motors installed & commissioned with starters — 7 Fresh Water + 7 STP motors.
  • Y-strainer installation — done for all 6 blocks (8×2.5" + 4×2" per block, 72 total).
  • Plumbing & blockages: 180+ complaints fixed. CATEGORY 1
  • Park-area percolation pits: 25 surveyed, 22 recovered & height-adjusted to the new park level; 3 not found. CATEGORY 1
In Progress
  • Fresh water automation controller — installation in progress; automatic water controller team to verify post motor installation.
  • New borewells: 2 of 5 drilled borewells still need motors fitted. CATEGORY 1
  • Cauvery Water Connection — BWSSB agreed in principle; EE Inbavalli (BDA) & AEE Naveen (BWSSB) visited Phase 2 (8 Aug); demand note to be issued; BDA confirmed will bear all expenses for 3 phases; larger-diameter pipeline from Safal Market side planned. BWSSB estimated timeline: 6 months to 1 year. Status update requested from officials on 21 Sep — awaiting reply. CATEGORY 1 🏆 MILESTONE
  • Water pressure issues — 13th & 14th floors, still to be resolved. CATEGORY 1
  • STP management: proper STP vendor with regular audits requested after weekly black-water reports — tender directed by Manivannan sir (31 Aug).
Not Done / Pending
  • Existing borewells: 3 of 4 have failed — near A block, near B block, and in Labour Colony — will not be restored. CATEGORY 1
  • New borewells: 1 of 5 drilled failed — no water found. CATEGORY 1
  • Yield reports pending for all new borewells — follow-up with Vinayak (Hombale). CATEGORY 1
  • Water filtration system. CATEGORY 1
  • Exit valve pending for all fresh water connections, including 13th & 14th floor extension. CATEGORY 1
  • Basement seepage — expansion joints (opened during basement cleaning) to be sealed.
  • Silt accumulation in pipes — ground sump-level filtration solution needed. CATEGORY 1
  • STP overhead tank discolored water (health hazard) — motors now installed with starters; auto-controller integration still pending to fully resolve discoloration. Responsible: Niranjan EE, Inbavalli AEE, Gunashekhar (Hombale). CATEGORY 1

2. Civil & General Maintenance

4 Done9 In Progress6 Pending
🏗️
Done
  • Maintenance of floors and basement.
  • Construction debris removed from common areas.
  • Exit ramp blockage issue resolved.
  • Parking data consolidated and updated through MyGate for easier tracking.
In Progress
  • Boundary wall construction on STP side started last week.
  • Dust mound clearance — discussed with Bhuvaneshwar EE & RCCL DGM; starts Mon 17 Aug 2026, ~10 days (target Wed 26 Aug 2026).
  • Wall behind sump & STP — to be leveled with sand to stop water logging.
  • Locking shaft doors & missing doors — list being compiled from members; Gunashekhar (Hombale) to rectify.
  • Back wall — STP side work sped up (significant progress); transformer side temporarily closed with sheets; F block work in progress. Bhuvan EE (5 Sep) directed it be completed urgently, with a drainage channel to the storm drains. Permanent resolution discussion (Inbavalli AEE & Niranjan EE with RCCL & Hombale) still pending.
  • Rear-side debris removal — continuous removal started 5 Sep after Bhuvan EE's follow-up with the RCCL DGM; SKRWA following up until it is fully cleared.
  • Recurring stilt debris cleanup — follow-up ongoing with Hombale to keep stilt areas clear.
  • Basement seepage — expansion joints to be sealed; SKRWA actively following up with BDA.
  • Housekeeping — stopped 4 Sep over non-payment; back to 4 cleaners, 1 gardener and 1 manager (7 Sep) against a normal 6 cleaners, 1 gardener and 1 manager. Full strength still to return.
Not Done / Pending
  • Entry & exit slab replacement — stalled; following up with Gunashekhar Sir (Hombale) for months, no visible update yet.
  • Basement parking water flooding solution.
  • Flooding near electric room / open ducts.
  • Second coat of painting.
  • Front gate elevation as per approved plan.
  • De-weeding of car parking areas.

3. Electrical, Fire & Safety

11 Done12 In Progress5 Pending
⚡
Done
  • CCTV installation with monitoring from front gate security cabin — recording now operational.
  • Lift AMC completed.
  • Common area streetlight repairs completed.
  • E Block ATS (Automatic Transfer Switch) — rectified by BESCOM & AXON.
  • D Block ATS — rectified by BESCOM & AXON.
  • Annual lift maintenance — B, C, D, E, F blocks done (2 lifts each: passenger + service). Only A Block remaining (2 lifts pending).
  • MCB electrical issues in A, D and E Blocks — rectified.
  • Follow-up with Ranjith Electrical Contractor (BDA) on MCB-related work — completed.
  • Speed breakers — 20+ installed (stilt 21 Aug 2026, basement completed too).
  • All 9 street lights fixed — B & C blocks, towards F block & road, near transformer & parking.
  • Snake-safety equipment — provided by BDA (7 Sep): 6 pairs of gumboots, 2 catching sticks, 2 rescue bags and 24 repellent devices; security team briefed.
In Progress
  • KSPCB Consent Renewal — show-cause notice, renewal in progress (Inbavalli AEE).
  • Boom barrier — requested for vehicle entry tracking.
  • Parking allotment/numbering (Konadasapura Phase 2) — flagged for discussion with BDA.
  • ⚠ Fire extinguisher refill — expiring end of this month, urgent renewal required. Inbavalli AEE to follow up. CATEGORY 1
  • Earth Pits Maintenance: 18 of 26 pits recovered, 8 more to go. JCB from Hombale deployed — also used to unearth 3 percolation pits.
  • Full lift servicing — had never happened before; first-ever full maintenance done for 5 of 6 blocks last month (July 2026). A Block's first full service still pending.
  • Tighter security implementation — gate protocols & visitor verification being strengthened.
  • Patrolling implementation — regular campus/night patrol coverage being set up.
  • Common area lighting (block-wise) — A Block done; SKRWA consolidating and working with Hombale block by block, others to follow.
  • FMS transition — technical evaluation under process (22 Sep). Hombale services end this month, escalated to the Zonal Commissioner on 19 Sep; BDA asked residents to form an ad-hoc/interim association to empanel the FMS vendor.
  • Gym-area lights — small lights approved by Manivannan sir; SKRWA coordinating with officials and the contractor for installation.
  • KPTCL underground line — 60+ kVA line being laid (22 Sep); transmission towers to be removed over the next few months. Piped gas (GAIL) for all 3 phases raised with BDA.
Not Done / Pending
  • DG Set: one missing as per approved plan; DG maintenance & backup DG required (critical during power failure).
  • Exit Gate as per approved plan.
  • Fire alarm systems and fire safety equipment. CATEGORY 1
  • 1 street light pole near the back wall is down — bulb bought; power connection to be extended during the back-wall borewell motor installation.
  • Transformer maintenance — recent power fluctuations reported in some flats.

4. Park & Environment

5 In Progress7 Pending
🌳
In Progress
  • Park work commenced 16 July — pavement laying underway.
  • Landscaping & debris removal — ongoing.
  • Jogging track construction — commenced.
  • Children's play area & walking track with gazebo — in progress, to be fenced.
  • Remaining park works to follow.
Not Done / Pending
  • Park development.
  • Jogging track.
  • Benches.
  • Lighting improvements.
  • Tree plantation / landscaping.
  • Waste segregation & organic composting — Inbavalli AEE to provide per-block wet/dry bins; Inbavalli AEE to issue work order to Hombale for dedicated STP person and organic waste converter machine, as proposed by Commissioner Sir.
  • Solid Waste Converter — Category 1, person to be assigned.
Note: This dashboard is for resident communication and tracking. Status can be updated after confirmation from BDA, Hombale, or the responsible execution team.